PROJECT 042 · LOS ANGELES, CA
Tower B — Civic Square
Phase
Structural · L3
Owner
Civic Square LLC
Schedule
2025-09-01 → 2027-04-30
Progress
38% · ON TRACK
RFIs Open
12
+3 this week
Photos · Apr
1,840
+218 vs last mo.
Daily Logs
47/47
100% submitted
Hours On Site
9,142
+412 this week
Open RFIs & field changes
12 OPEN · 4 IN REVIEW
| ID | Title | Trade | Filed | Status |
|---|---|---|---|---|
| RFI-0118 | Rebar spacing at column C-7 | Concrete | 04-25 · 14:30 | Open |
| RFI-0117 | HVAC rough-in clash · L4 corridor | MEP | 04-24 · 16:08 | In Review |
| RFI-0116 | Door swing conflict · stair B | Architectural | 04-24 · 11:42 | Open |
| RFI-0115 | Slab thickness deviation L3 | Structural | 04-23 · 09:14 | Escalated |
| RFI-0114 | Conduit run · electrical room | MEP | 04-22 · 15:30 | In Review |
| RFI-0113 | Curtain wall mullion alignment | Architectural | 04-22 · 08:55 | Resolved |
Today
APR 2514:30
RFI-0118 filed by J. Ortega
Voice note · 1:24 · 3 photos
11:42
Concrete pour completed · L3
12 cu. yd. · Inspector signed off
10:08
Inspector arrived
Pre-pour walkthrough · L3
09:14
Steel delivery · bay 3
4 photos · GPS tagged
07:42
Crew check-in
14 workers · 4 trades
07:00
Site open
Foreman J. Ortega